Junipero Serra Playground Project Update: Three Week Look-Ahead [June 19, 2007]

This memo from our project director provides an overview of the work at JSP and what is in store for the coming three weeks.
Good Morning Junipero Serra neighbors,
The Junipero Serra project is progressing. The formwork for the foundations is being installed as well as the rough-ins for the utilities. The Contractor expects the rebar to be delivered by the end of June and the concrete foundations will be poured the second week of July. I have attached the 3-week look ahead schedule in case anyone is interested in more detail.
Meghan Tiernan, Project Manager